Three years after its soft opening, Dhaka airport's third terminal finally has a date to start working. The 15-year concession agreement with a Japanese consortium is likely to be signed on 30 November, according to sources at the Civil Aviation Authority of Bangladesh, and partial operations are planned from 16 December, Victory Day, with four flights. The Civil Aviation Authority has scheduled a press conference for 29 November to brief journalists on the signing.

The Cabinet Committee on Economic Affairs approved the deal in principle on 23 November, at a meeting chaired by Finance and Planning Minister Amir Khosru Mahmud Chowdhury. Civil Aviation and Tourism Minister M Rashiduzzaman Millat said after the meeting that the government hoped to sign the agreement by the end of November. The consortium brings together Japan Airport Terminal Co Ltd, Sumitomo Corporation, Nippon Koei and Narita International Airport Corporation.

The dates, and the long ramp

Estate News — Find your dream home

The opening will be modest. Four flights, with Biman Bangladesh Airlines operating the inaugural flights: two departures and two arrivals, to Malaysia, Dubai, Bangkok and Singapore. The government had initially planned to start at 25 percent capacity, but the consortium could not reach that level immediately, and the decision was taken to start with four flights and build up. The consortium takes over within 15 days of signing. Operational commencement follows eight months after handover, at 25 percent capacity. Full operations could take up to 14 months from 16 December, and the existing international terminal will keep running meanwhile.

The terminal itself is more than 99 percent complete. Built with support from the Japan International Cooperation Agency at a revised cost of Tk 22,213 crore, it has been under implementation since 2016, with completion due in 2027. It has not begun commercial operations despite a soft opening in October 2023. Three years of a finished building standing idle is the backstory to every date in this deal.

The money

Advertise on Estate News

Bangladesh negotiated a better share than the one agreed by the previous government. The country's share of the terminal's revenue was raised from 15 percent to 27 percent. There will be no revenue share in the first eight months after handover, then a 13.5 percent share during a six-month transitional phase. Once fully operational, the consortium will pay $2.10 per passenger, equal to 20 percent of passenger revenue, and 27 percent of cargo revenue, at $11.50 per tonne. An upfront fee of $8.1 million, about Tk 100 crore, is also part of the deal, along with an embarkation fee of $12.50 per departing international passenger.

Biman keeps up to 50 percent of international ground handling. One condition runs through the 15-year term: no new airport within a 100-kilometre radius for 15 years.

What it means for the airport corridor

A working Terminal 3 changes the daily life of the airport corridor, from Uttara through Tongi to the airport road. The first flights will be a trickle, four a day, and the full operation is more than a year away. But the direction is set. Passengers who now queue through the old international terminal will, over time, move into a building designed for far larger numbers. The shops, hotels, offices and housing along the corridor will feel the change in stages, as the flight count rises.

Estate News covered the operator's appointment in "Terminal 3 Gets Its Operator: A Japanese Consortium Takes Dhaka Airport's Newest Wing", the newest planned blocks nearby in "Uttara Sector 16: Dhaka's Newest Planned Blocks Take Shape", and the underground line redrawing the city in "MRT Line-1: The Underground Metro Redrawing Dhaka's Map". The signing date to watch is 30 November. The first flights, if the dates hold, land and leave on 16 December.