Delay is the most common complaint in Dhaka's under-construction flat market, and also the most confusing. A developer may cite approvals, material prices, labour shortages, utility connections or financing. Some reasons are genuine. Others are a cover for poor planning or for money diverted to another project. From the buyer's side, the reason matters less, at first, than the response: what the agreement says, what is documented, and what is done next.

This article gives general information only. It is not legal advice, and it does not replace advice from a qualified lawyer about a specific agreement or dispute. Procedures, forums and remedies can vary with the contract, the project and the facts, so a buyer facing a significant delay or financial loss should seek independent legal advice promptly.

First, establish the facts in writing

Estate News — Find your dream home

The first step is not a confrontation. It is a file. Gather the signed agreement and all annexes, the payment schedule, every payment receipt and bank record, booking documents, the brochure or specification sheet if it was part of the sale, and every message, email and letter exchanged with the developer. Note the promised handover date, any grace period, any penalty or compensation clause, and any written extensions already agreed.

Then put the delay in writing to the developer. A short, factual letter or email — stating the agreement date, the promised handover date, the payments made, the current status as the buyer understands it, and a request for a revised, specific completion date — creates a record that verbal complaints do not. Keep copies of everything sent and received, with dates. If site visits are made, note the date, what was seen and who was present.

Buyers acting together often have more leverage than buyers acting alone, but joint action should also be documented and lawful. A buyers' group that shares verified information, keeps minutes and communicates through a single written channel is more credible than scattered individual complaints.

Read the delay clause before deciding what to demand

Not every delay entitles the buyer to the same remedy. The agreement may provide a grace period, a penalty rate, a right to cancel after a defined period, or none of these. Some agreements require the buyer to give formal notice before a remedy applies. Others link compensation to a specific trigger, such as failure to hand over by a revised date.

That is why the first legal question is usually a contractual one: what did the parties actually agree? A lawyer can advise whether a penalty clause is enforceable on its terms, whether cancellation and refund are available, and what notice must be given. Buyers should not assume that a general sense of unfairness, however justified, automatically creates a right to a refund or to stop paying instalments. Stopping payments without advice can itself create a dispute, so that step should be taken only after legal review.

Negotiate, but negotiate in writing

In many delayed projects, a negotiated outcome is faster and less costly than a formal dispute. Options buyers commonly explore include a revised handover date with a written penalty for further delay, compensation for rent or additional costs incurred because of the delay, a change to the payment schedule so that remaining payments follow verified progress, or, where the buyer no longer wishes to proceed, cancellation on agreed refund terms.

Whatever is discussed, the outcome should be recorded in a signed written amendment, not left as a verbal promise or a message from a sales officer. The amendment should state the new date, what counts as handover, the penalty or compensation if that date is also missed, and the status of all previous payments. If the developer offers a different flat, a different project or additional facilities instead of compensation, that offer and its conditions should also be in writing and checked independently.

Advertise on Estate News
A delay becomes harder to resolve the longer it stays verbal. Put the date, the demand and the reply in writing — every time.

Practical checks while waiting

  • Visit the site regularly and record progress with dated notes and photographs, noting which works are actually under way.
  • Check, through independent advice, whether approvals, utility connections or common-area works are the real bottleneck, rather than accepting a single explanation.
  • Review your own finances: additional rent, loan instalments and the cost of waiting, so that any compensation claim reflects real loss, not only frustration.
  • Do not accept handover of an incomplete flat without a written defects list and a deadline for correction, unless advised otherwise.
  • Keep loan and tax records up to date, and inform your bank if the delay affects disbursement or repayment planning, after taking advice.

When negotiation fails: routes to discuss with a lawyer

If written negotiation does not produce a revised date or a remedy, a lawyer can advise on the formal routes available on the facts of the case. In general terms, these may include a formal legal notice, mediation or arbitration if the agreement provides for it, a civil claim for enforcement of the agreement or for refund and compensation, and complaints to relevant regulatory or consumer-protection authorities where their jurisdiction applies.

Each route has costs, timelines and evidence requirements, and the right choice depends on the amount at stake, the developer's solvency and progress, and the strength of the buyer's documents. That assessment is precisely why early legal advice matters: a buyer who waits until the project has stalled completely may find fewer practical options than a buyer who acted when the first deadline was missed.

Buyers should also be cautious about informal pressure tactics, withholding payments without advice, or signing a new document under pressure to "regularise" a delay. Any new paper that changes the handover date, waives compensation or alters the payment schedule should be reviewed before it is signed, because it may affect rights that existed under the original agreement.

Protecting the next buyer — including yourself

A delayed project teaches a lesson that should be carried into any future purchase: favour agreements with clear handover dates, defined grace periods, meaningful delay penalties, milestone-linked payments and a written defects procedure. Check the developer's track record on previous projects, not only the current brochure. And keep every document from the first booking form onwards, because in a dispute, the buyer with the complete file is in a materially stronger position.

Delay is not always a sign of bad faith, and not every delayed project fails. Some recover, complete and hand over. But a buyer who documents the delay early, negotiates in writing and takes timely legal advice preserves options that a buyer who waits in silence may lose. In a market where a flat is often a family's largest purchase, that discipline is not bureaucracy. It is protection.