The dates are now exact. The signing ceremony for the third terminal of Hazrat Shahjalal International Airport will take place at 7pm on Monday 30 November at the InterContinental Dhaka, with Civil Aviation and Tourism Minister M Rashiduzzaman Millat expected to attend. The day before, on Sunday 29 November, the Civil Aviation Authority of Bangladesh will hold a press briefing at its headquarters auditorium, where CAAB Chairman Air Vice Marshal Md Mostafa Mahmood Siddiq will outline the concession. After months of uncertainty, the terminal that has stood nearly finished and unused has a calendar.

The CAAB board approved the consortium's terms at its 321st meeting on 10 November, following a review. The Cabinet Committee on Economic Affairs, chaired by Finance and Planning Minister Amir Khosru Mahmud Chowdhury, approved the 15-year concession agreement on 23 November. CAAB has begun trial operations at the terminal. The consortium that will operate it brings together Japan Airport Terminal Co Ltd, Sumitomo Corporation, Nippon Koei and Narita International Airport Corporation. The consortium takes over within 15 days of signing, and operational commencement follows eight months after handover, at 25 percent capacity.

Four flights on Victory Day

Estate News — Find your dream home

Partial operations begin on 16 December, Victory Day, with four flights initially. Biman Bangladesh Airlines will operate the inaugural flights: two departures and two arrivals, serving Malaysia, Dubai, Bangkok and Singapore. Full operations will follow within 14 months of handover. The terminal, built with support from the Japan International Cooperation Agency at a cost of Tk 22,213 crore and under implementation since 2016, is more than 99 percent complete. It has stood unused for around 23 months despite a soft opening in October 2023. CAAB says around 600 management and operational issues have now mostly been resolved.

The capacity change is the point of the whole project. The airport handles around 80 lakh passengers a year today. With the third terminal fully operational, capacity rises to between 1.6 crore and 2.2 crore passengers a year. The terminal covers 230,000 square metres. One condition in the deal bars a new civilian airport within a 100-kilometre radius for 15 years, a restriction the minister has defended on the basis of a feasibility study that found no immediate requirement for another airport so close to Dhaka.

Estate News free property calculators

The money in the deal

Bangladesh negotiated a better share than the one agreed before. The country's share of revenue was raised from 15 percent to 27 percent through negotiation, according to the minister. There is no revenue share in the first eight months, then 13.5 percent during a six-month transitional phase. Once fully operational, Bangladesh receives $2.10 per passenger, equal to 20 percent of passenger revenue, and 27 percent of cargo revenue, at $11.50 per tonne. The consortium pays an upfront fee of $8.1 million, around Tk 100 crore. The embarkation fee for a departing international passenger at the new terminal is set at $12.50. Biman keeps up to 50 percent of international ground handling.

What it means for the airport corridor

A working Terminal 3 changes the map north of Dhaka. Uttara, Tongi and the airport corridor live on the airport's traffic: hotel rooms, guest houses, transport, shops and flats for the staff who keep the flights moving. For two years, the corridor has waited beside a finished building with no passengers. From 16 December, the first four flights start to fill it, and the ramp-up to full operations over 14 months gives landlords, shopkeepers and developers a timetable to plan around instead of a rumour.

The corridor's housing has always been shaped by the airport. Flats near the terminal rent to airline staff, frequent flyers and families who want the city without the centre's prices. A terminal that works, with more flights and more jobs, supports that demand. A terminal that stalls again would leave the same streets waiting. The signing on Monday, the briefing on Sunday and the first flights on 16 December are the three dates that decide which of those futures arrives. Estate News has followed the terminal's long wait since the soft opening, and the concession approval last week. This week, the waiting has a schedule.