Commuters who crawl through Karwan Bazar every morning have waited years for one ramp. The Panthakunja ramp of the Dhaka Elevated Expressway, which lets vehicles climb onto the expressway from the Panthapath area, is now close to opening, and the reports agree on the season even if they differ on the month. Prothom Alo reported January. The Business Standard reported early February. New Age pointed to March. All three place it before Eid-ul-Fitr, which falls in March, and all three say the same thing about why it matters: it will take pressure off the Tejgaon ramp, which carries the load today.
The ramp will work in one direction only. Vehicles will be able to enter the expressway through it, but not exit, according to the Bangladesh Bridge Authority. That detail matters for anyone planning a route home. The entry will help traffic heading out of the city centre and onto the elevated road. It will not help anyone trying to get down into Panthakunja itself.
Kamalapur by June, the rest by 2028
Two entry and exit ramps at Kamalapur are targeted for completion by June 2027. Their opening had originally been proposed for 2027, and the Bridge Authority has now instructed the project's private investor to finish them by June. Bridges Division Secretary Mohammad Abdur Rouf told Prothom Alo on 10 November that the contractor had been told to complete construction up to Kamalapur by then, and that the section was expected to become operational by June.
The full picture is slower. Overall physical progress stood at 80.72 percent as of September 2026, according to project data. The Kaola to Banani stretch, 7.45 km, is complete. Banani to Moghbazar, 5.85 km, is at 87 percent. Moghbazar to Kutubkhali, 6.43 km, is at 22.45 percent. The remaining sections, from Kamalapur to Kutubkhali and from Panthakunja to Palashi, are targeted for completion by 31 December 2028, and the Bridge Authority says the deadline will not be extended.
Construction is moving slowly in Maniknagar, Kamalapur, TT Para and Jatrabari. Work at Panthakunja itself was suspended for a year. The expressway runs from Kaola, south of Hazrat Shahjalal International Airport, to Kutubkhali on the Dhaka-Chattogram Highway, about 47 km including 31 ramps, of which 27 km is ramps. The Kaola to Farmgate section opened on 3 September 2023, and the down ramp near the FDC rail gate opened on 20 March 2024. The project, a public-private partnership, began construction in January 2020 at an estimated cost of Tk 8,940 crore on 2011 prices. Its original completion date of June 2024 was missed.
What the ramps mean for the neighbourhoods below
For Tejgaon, Karwan Bazar and Kamalapur, the ramps are about access, not about prices. A ramp that works takes cars off the streets below and onto the elevated road, and it shortens the trip to the airport for everyone who lives or works nearby. That is the practical gain, and it is the one the Bridge Authority is promising first.
There is a caution attached, and it deserves a line of its own. New Age reported on 25 November that planners are concerned the Panthakunja entry ramp, at the SAARC Fountain, could worsen congestion on the roads below it, since cars queuing to enter will gather where traffic already knots. The concern is a planner's warning, not a verdict, but it is worth carrying, because the streets around Panthakunja, the park, the fountain and the Karwan Bazar intersection are already among the busiest in the city.
Property follows access, but slowly, and only where the access actually works. Flats and offices near a working ramp gain a shorter commute to the airport and to the north of the city. Shops near the ramp mouth gain passing trade and lose easy parking in the same move. Kamalapur, with its railway station and its two ramps due by June, is the bigger change of the two, because it connects the expressway to the city's main rail gateway. Until the Moghbazar to Kutubkhali stretch is built, though, the expressway remains a road that starts at the airport and stops short of the south. The Panthakunja ramp will open a door. The road beyond it is still under construction.